Burwood Brickworks is set to be a world leading retail & public space upon its completion. The approx. 12,700m2 space will comprise of retail outlets, public amenities and will house approx. 2,000 residents – the centre is seeking to be a part of the world’s most sustainable shopping districts due to its unique construction.

To allow excavation and then development on the 78 Middleborough Rd property, a retaining wall was required along the perimeter and adjacent RSPCA property.

Our Role

Geotech’s work involved the construction of a 300m long by up to 10m high retaining wall.
The detailed scope of works included:

  • Drilling, inserting, then grouting 800no. 4.5m X 25mm galvanised steel soil nails into siltstone wall at 1.5m spacing
  • Detailed excavation around the nails to ensure a flat and uniform wall surface
  • Fixing strip drains between the nails to prevent any water undermining the wall
  • Fixing RL81 mesh along the wall and tying onto the nails
  • Shotcrete spraying the wall 180mm thick
  • Creating a 300m spoon drain along the top to allow drainage into pits at either end of wall

Disciplines covered

  • Soil nail wall

Contáctanos. Nuestro horario de oficina:
Lun - Vie 8:30 - 17:00

HEAD OFFICE - MELBOURNE

11 Eastern Rd, South Melbourne VIC 3205

padding-bottom: 5%; "> GEOTECH OFFICE LOCATIONS

HEAD OFFICE - MELBOURNE

174 Turner Street, Port Melbourne, VIC 3207

PERTH

Level 3, 195 Great Eastern Highway, Belmont, Western Australia 6104

+61 8 9488 8212

BRISBANE

Level 2, 100 Melbourne Street, South Brisbane, Queensland 4101

SYDNEY

Level 2, 55 Harrington Street, The Rocks, New South Wales 2000

Síguenos

Suscribir

Derechos reservados © 2020 Geotechnical Engineering.